Executive summary

Specialist external legal advice is required to enable the effective preparation of an e-counting solution procurement, and related contract documentation, in the light of market and technological changes and in particular to reflect the use of Agile project methodologies to optimise delivery. The advice is being provided by Eversheds Sutherland. Approval of the related expenditure is sought from the GLRO. 

 

Decision

That the GLRO approves expenditure of £40,176 on specialist legal services from Eversheds Sutherland which are required to prepare an optimal e-counting solution tender. 

 

Part 1: Non-confidential facts and advice

Introduction and background

1.1    GLRO Form 20-02 approved the decision to commence a procurement exercise to appoint an e-counting contract for the 2020 Mayor of London and London Assembly Election, with the caveat that, should no tender prove satisfactory in terms of quality and/or affordability, a contract will not be awarded and consideration will be given to counting manually. 

1.2    A contract notice advertising and setting out the details of the contracting opportunity will be published in the Official Journal of the European Union (“OJEU”).

1.3    The GLA requires the e-counting software to be developed using an Agile methodology; specifically, it is to be developed using the following, iterative, Agile ceremonies:

•    Initial discovery, followed by analysis workshops
•    User research workshops
•    Two to three-week sprints which include system testing
•    Backlog of stories
•    Sprint planning and prioritisation sessions
•    Daily stand-ups
•    Retrospectives

1.4    This along with significant technological, market and regulatory developments since e-counting services were last procured (for the 2012 and 2016 Mayoral and Assembly elections) has necessitated the specialist review of, and advice on, documentation required for the procurement of a 2020 e-counting solution.

1.5    An estimate has been sought and obtained, via TfL’s Legal Panel, from Eversheds Sutherland in this regard covering amongst other matters:    

•    review the current contract, uplifting and redrafting as necessary to take account of technological, regulatory and other legal developments; 

•    consideration of telecoms regulatory aspects and potential impacts for example, of the new Electronic Communications Code and drafting of additional clauses as may be required; 
•    consideration of changing the data protection terms in line with forthcoming application of the General Data Protection Regulation;

•    reviewing wide and local area networking technical requirements and drafting WAN/LAN representations and warranties as may be required;

•    high level review of other technical requirements from a legal perspective to seek to ensure any contractual alignment and flag any material legal issues including telecoms and IT legal review; 

•    assisting with legal clarification questions from bidders: 

•    high level legal review of Schedules produced by successful bidder once agreed by the GLA  to the E-counting Agreement (as produced by GLA and/or its chosen supplier) to ensure consistency with front end terms for final contract and production of final contract version; and

•    associated briefings, meetings and calls to go through draft contract with particular focus on legal areas for potential change/take instructions for areas of change

The estimate is presented as a range and it is acknowledged also that matters/issues may arise during the course of the project which may necessitate additional advice. In the event that additional advice is required further supplementary estimates and related approvals will be sought.  
 

Objectives and expected outcomes

    Impact Assessments and Consultation

2.1    None

    Equalities Comments

2.2    None

Risk

2.3    In light of significant technological, market and regulatory developments since e-counting services were last procured, preparing tender and contact documentation without securing specialist IT, telecoms and related legal advice risks the sub-optimal: 

•    procurement and delivery of an e-counting solution; 
•    discharge of the GLRO’s duties; and    
•    protection of the GLA’s interests.       
 

Financial comments

3.1    The GLRO is being asked to approve expenditure of £40,176.  

3.2    It is anticipated any future expenditure will be contained within the elections budget. For reference, the e-counting award in 2012 amounted to £4.1m and in 2016 to £3.4m (a discounted rate, as it was the second election of a two-term contract). The overall cost of the election was £18.7m in 2012 and £18.2m in 2016. 
 